How Long Does a Home Renovation Take in Tbilisi?
Home renovation is one of the most exciting — and sometimes stressful — projects a homeowner can take on. Whether you’ve purchased an old apartment in central Tbilisi or want to modernize your existing home, one of the first questions that comes to mind is: how long will the renovation take?
The answer depends on several factors, including the property’s size, condition, type of renovation, and how efficiently the project is managed.
In this article, we’ll break down what to expect and give you a realistic idea of how long your renovation might take in Tbilisi.
-
1. The Planning Stage (2–4 Weeks)
Before construction starts, there’s a vital planning and preparation period. During this time, you’ll work with designers, architects, and contractors to define your vision and scope of work.This stage typically includes:
- Object size — a small studio renovation can be completed in 4–6 weeks, while renovating a 120–150 sq.m apartment takes 4–5 months.
- Type of work — cosmetic repairs are much faster than full renovations, which include installation of water, electrical, and heating systems.
- Design complexity — modern, minimalist designs require less time, while non-standard design elements extend the process.
- Material availability — delays are often related to the delivery of imported materials.
- Team competence — an experienced team completes the process steadily and within the planned timeframe.
-
Cosmetic renovation — 3–8 weeks
If the apartment needs only light updates, such as:
- Painting walls
- Replacing or refreshing flooring
- Changing lighting
- მცირე სანტექნიკური სამუშაოები
- Installing wallpaper
Such work typically takes 3–8 weeks..
Cosmetic renovation is ideal for apartments prepared for rent or homes where the main engineering systems are in good condition.
-
Full renovation — 3–6 months
A full renovation of a newly built apartment in Tbilisi usually includes:
- Rough construction work
- Electrical wiring
- Water and sewage systems
- Waterproofing
- Drywall constructions
- Bathroom setup
- Tile, laminate, or other flooring
- Wall finishing
- Doors and windows
-
Capital renovation of an old apartment — 4–7 months
Renovating an old apartment is more complex because it often requires:
- Replacing old communications
- Demolishing and rebuilding walls
- Solving problems with mold, moisture, or cracks
In such cases, the renovation time increases and often exceeds 5–7 months..
Old buildings frequently have unexpected “surprises,” so you should consider an additional time buffer.
-
What causes the biggest delays?
The most common reasons for renovation delays in Tbilisi are:
- Delayed delivery of materials
- Incorrect planning or schedule
- Custom furniture production time
- Changes in design after work has started
- Mistakes by an unprofessional team
To avoid these problems, it’s better to work with a company that:
- Provides a fixed schedule
- Sends weekly reports
- Works with a contract
- Manages material logistics
- Has its own engineering team
-
How to reduce renovation time?
Here are some tips to accelerate the process:
- Start planning early — design and budget should be approved in advance.
- Choose a reliable and experienced company — a professional team saves most of the time.
- Do not change the design during the process — changes almost always increase deadlines.
- Organize material deliveries — it’s important to have materials on-site on time.
Conclusion:
The average duration of home renovation in Tbilisi ranges from 1 to 6 months,but this depends on the type of property, scale of work, and the experience of the chosen team.A well-planned schedule, high-quality project documentation, and a professional renovation company will help you achieve a quality result on time and without unnecessary stress.